Schedule activity to occur after previous activity completed, not from anchor date.

New Member
Posts: 4
Country: United States

Schedule activity to occur after previous activity completed, not from anchor date.

I'm wondering if there's a way to make an activity in an activity series occur after the previous activity is done, rather than occuring after the anchor date.

 

Thank you!

Moderator
Posts: 4,395
Country: USA

Re: Schedule activity to occur after previous activity completed, not from anchor date.

bdbogart,

 

Unfortunately, activity series can only be setup by anchor dates.  A possible work around if when clearing an activity, you can schedule a follow up activity.

 