Is there a way to make tasks roll over to the following day if they are not completed? How can I do this? Thanks!
Copper Elite Contributor
Posts: 227
Country: New_Zealand

Re: Calender tasks roll over to following day

I don't know of any way of getting automatic roll-over (personally that would annoy the heck out of me as I like to have a picture of what is getting behind and whether I am dragging the chain on something) but you can drag and drop them in week or month calendar view, which saves going through the 'Reschedule Activity' route.  Cheers.
Nickel Super Contributor
Posts: 441
Country: UK

Re: Calender tasks roll over to following day

Tools -> Prefs -> Calendar & Scheduling Tab -> Scheduling Prefs -> tick the box for automatically roll over activities