Activity Follow Up Start Date Field - Not Accepting K/B Entered Date First Time

Accepted Solution Solved
Bronze Contributor
Posts: 1,393
Country: USA
Accepted Solution

Activity Follow Up Start Date Field - Not Accepting K/B Entered Date First Time

When I clear an activity that will also have a follow up, I enter the cursor in the Start Date of the follow up being scheduled.  It is highlighted and I then enter a date from the keyboard.  The date shows correctly as entered such as 4/15/13.  When I tab out of the field, it diverts back to today's date. 

 

If I go back and enter the date again in exactly the same format and tab out, the date field is updated. 

John Purdy
ACT! Premium 2016 (V. 18)
Main: HP 9470M 8GB, Win 10 Pro, & Exchange 2013 & Office 365, 32bit
Remote: Dell XPS Ultrabook with 4GB & Win 10 Pro, Office 365 32bit & Exchange 2013

Accepted Solutions
Solution
Accepted by topic author jnpurdy
‎09-25-2015 03:20 AM
Platinum Super Contributor
Posts: 5,275
Country: USA

Re: Activity Follow Up Start Date Field - Not Accepting K/B Entered Date First Time

John,
This is a known issue and has been reported to Development, for activities with a Start Time of 'timeless'. Are you experiencing this issue for other types?

A work-around at this time is to use the drop-down calendar to choose a different date.
Greg Martin
Sage

View solution in original post


All Replies
Solution
Accepted by topic author jnpurdy
‎09-25-2015 03:20 AM
Platinum Super Contributor
Posts: 5,275
Country: USA

Re: Activity Follow Up Start Date Field - Not Accepting K/B Entered Date First Time

John,
This is a known issue and has been reported to Development, for activities with a Start Time of 'timeless'. Are you experiencing this issue for other types?

A work-around at this time is to use the drop-down calendar to choose a different date.
Greg Martin
Sage