Ihave multiple tasks set for the same day.

When I view mytasklist, there is one name and a + mark, allowing me to expand but it takes me to a lookup screen

Is there a way to have the view list automatically show all tasks ?

 

Thanks

 

Copper Super Contributor
Posts: 110
Country: USA

Re: Expand task list in view

Hello Doug,

 

I like the Task List View because it can show you as many or as few of your scheduled tasks as you want.

 

Q: "Is there a way to have the view list automatically show all tasks ?"

A: The filter row (Dates, Types, Priorities) at the top is how you control what you get to see.

 

Q: "When I view mytasklist, there is one name and a + mark, allowing me to expand but it takes me to a lookup screen"

A: The + sign can be found in the Schedule With column when there is more than one person included in the activitiy.

     - You will only be able to see the first person in the list in this view.

       Double click in the activity row to see them all in the Schedule Activity dialog box. 

     - When you click the hyperlink it is a short cut to looking up everyone in the Schedule With field.

 